Ques. What is the
Sectoral eligibility for availing loan?
Ans.
Biomass Power:
The projects having capacity of 1 to 7.5 MW with minimum steam
generation pressure of 63 ata are eligible.
Biomass Cogeneration:
-
Small scale
Cogenration Projects (except sugar industries ) up to 7.5 MW
installed capacity with steam generation pressure of 63 ata
are eligible.
-
The projects having
above 7.5 MW installed capacity (both for sugar and non-sugar
industry) with steam generation pressure of 63 ata are
eligible.
Ques. Is DPR required to be prepared by a
reputed consultant?
Ans.Yes, Consultants, who
are involving in the power sector, are preferred.
Ques. What are the appraisal requirements?
Ans.
Project should have
been registered with JREDA. Detailed project report along with
cost estimates etc and clarifications requested by JREDA should
have been submitted / clarified.
Ques. What are the eligibility requirements
for availing loan?
Ans.
For eligibility
requirements please refer to the General Eligibility Conditions
of JREDA's Financial Guidelines.
Ques. What is the Security that is required
to be furnished?
Ans.
For security
requirements please refer to Security (Project Financing Scheme)
of JREDA's Financial Guidelines.
Ques. How much time does it take for the loan
to get sanctioned?
Ans.
Normally, JREDA
sanctions a project within 90 days of registration of the same,
provided complete details / papers are submitted by the
applicant and the project is found viable from technical,
financial and legal point of view.
Ques. What is the capacity limitation?
Ans.-
Biomass Power:
1 to 7.5 MW
Biomass Cogeneration:
|